Mr. Lalduhawma, Engineer - Vision City Project

Report in the month of December, 2009

  • Kitchen & Dining Hall construction: Plastering (two coats), elevation works for verandah, making slope roof, making architectural design, electrical works, plumbing works is in progress. Roof for front verandah, staircase is completed.

  • Family Accommodation construction: Rising of column for 1st floor, centering and shuttering of 1st floor beams and slab is in progress. Brickworks are also going on.

  • Gas station works for Kitchen is going on, visited SAIACS and FMC buildings in Bangalore to see the Kitchen, room arrangements.

Prayer Concerns:

  • Pray for the safety of workers and God’s wisdom upon us.

  • Pray that the works will be completed as soon as possible.

Report in the month of November, 2009

  • Worked on completing the work of Kitchen & Dining Hall’s Brickworks, Plastering, elevation works for verandah, making slope roof, making architectural design, electrical works, & plumbing works.

  • Family Accommodation construction: Laying of cement concrete slab (roof) Ground floor is completed.

  • Working on budget of construction of Gas station for Kitchen, Requirement of Chimney for Kitchen and Fabrication works for Toilet, Dining Hall office is also worked out.

  • I thank God for opening His Mission works in other ministries and get connected with other leaders.

Pray for:

  • Pray for the safety of workers and God’s wisdom upon us.

  • Pray that the construction works will be completed as soon as possible.

Report in the month of October, 2009

  • Kitchen & Dining Hall construction – Brickworks for outside walls and internal walls is in progress.

  • Family Accommodation construction – Shuttering & centering of slab for 2nd, 3rd & 4th block is completed.

  • I thank God for His protection though sometimes I am struggling with health problems I can resume the works by God's Grace.

Prayer Concerns:

  • Pray for the safety of workers and God’s wisdom upon us.

  • Pray that the works will be completed as soon as possible.

Report in the month of September, 2009

  • Kitchen & Dining Hall construction: shuttering & steel works, laying of cement concrete for roof slab has been completed. Formworks also removed, brickworks are also started.

  • Family Accommodation construction: shuttering & steel works, laying of ground floor slab has been completed for 1st block. Shuttering of slab for 2nd and 3rd block is in progress and brickwork also started for walls.

  • Readings of Wind data logger has been sent to the company through Mr. Adam Allard.

  • I thank God for His wisdom pour upon me to handle the works without much difficulty.

 Please pray for:

  • Needed fund for the Vision City.

  • The safety of workers and God’s wisdom upon all of us.

  • The works will be completed as soon as possible.

Report in the month of August, 2009

  • Working on the construction of Kitchen & Dining Hall construction. Shuttering, centering & laying steel reinforcement of roof beam and slab is in progress.

  • Family Accommodation construction: Plinth Beam, laying of Cement concrete for Flooring, Stone works & back filling for Corridor, Raising Column for Ground floor slab has been completed.

  • Construction of Parking Shed, and Renovation & repairing works are done.

  • Readings of Wind data logger has been sent to the company through Mr. Adam Allard.

  • I encouraged by ongoing Vision City Construction, I really thank God for His guidance in everything.

Pray for:

  • The Vision City funds.

  • The safety of workers and God’s wisdom upon us.

  • The works will be completed as soon as possible.

Report in the month of July, 2009

  • Kitchen & Dining Hall construction – Raising column, plain cement concrete flooring, shuttering & centering for roof beam and slab is in progress

  • Family Quarter construction – Stone works, R.C.C & Steel works for the plinth beam, back filling is in progress

  • Rain harvesting works, making of water channel, connecting pipes to the water tank for collecting rain water.

  • Construction of Library room.

  • Readings of Wind data logger has been sent to the company through Mr. Adam Allard.

Please Pray for:

  • The funds for Vision City.

  • The safety of workers and God’s wisdom upon us.

  • The works will be completed as soon as possible.

Report from January to June, 2009

  • Rising of North side compound wall by 3 foot & Barbed wire fencing is been done.

  • Shifting of Agriculture power line to Industrial High Tension line has been done.

  • Publishing of Tender notice for construction of Kitchen & Dining Hall and Family Quarter.

  • Construction of Vision City building has been started.

  • Construction of Vehicles Parking Shed near Generator room has been done.

  • Readings of Wind data logger has been sent to the company through Mr. Adam Allard.

Pray for:

  • The safety of workers since they are working in hot sunlight, there is a possibility of getting sunstroke etc. also other harmful things like snake and scorpion bitten.

  • Progress of Vision City so that the contractors can complete in a specified time.

  • God wisdom on Contractor people and Site Engineer of Vision City.

Report in the month of December, 2008

  • Transformer yard fencing has been done.
  • Construction of toilets for labour work is in process.
  • Raising of Compound wall (North side) with angle Iron for fencing work is in process.
  • Preparation of BOQ, structural design etc. for Vision City work is still going on and to be completed before 15th January, 2009.
  • I went to my native place for Christmas vacation, and I was very much encouraged by Church members by praising and welcoming me since I am a Christian Missionary.
  • Pray for the Funds need to be raised for Vision City Construction.
  • Pray for Vision City Construction which is supposed to start soon.
  • Pray for works going on such as Compound wall, shifting electric poles and tender calling for Vision City Construction.

Report in the month of November, 2008

  • Worked for the Construction of temporary Business room.

  • Worked for the Connection of 3-phase current in Transformer.

  • Installation of meter box in Transformer.

  • Met with IMA Chairperson regarding architects for Vision City.

  • Appointed letter given to Architect for Vision City.

  • Met with Legal adviser for Vision City

  • I really encouraged in seeing some labors are really talented in their works of field. So as a mission worker we really need to concentrated and putting our hearts in what we do.

  • Pray for funds needed in Vision City Construction.

  • Pray for Vision City Construction starting soon.

  • Pray for wisdom of Site Engineer to look after the construction works.

Report in the month of October, 2008

  • Met Dr. Kamala Chiranjeevi & Mr. Santa Kumar (Seva Bharat) for selecting Architect for Vision City Construction.
  • Met Architect Mr. N. Anand in ECIL and Mr. Jasper Dawson through E-mail and took their fees terms and conditions.
  • Met Advocate Mr. Nirmal Kumar and Mr. Vikranth Kumar and went to Secunderabad court for legal adviser of Visio City Project, IMA.
  • Had Site Visit of Mr. Prasana Kumar (Architect) on going & completed projects, and It’s a great thing that some of the project s done by the architect Mr. Prasana kumar, it’s really impressed me as he has done excellent job.
  • Pray for good architect, & building for construction projects.
  • Pray for all the legal procedures to be done for Vision City.
  • Pray for the funds to be raised.

 

 

 

back

©2006 India Missions Association. All rights reserved
For further information please feel free to contact us at ima@imaindia.org
Powered by www.jasminecorp.net
Kindly send your donation by MO/Draft/Cheque drawn to 'India Missions Association', Hyderabad designated for Mr. Lalduhawma to the below address
Our Contact Address:
IMA, 5-47, Kundanpally Village, Near Vardhana School, Godumakunta Panchayat, Keesara Mandal, R.R. District - 501301 (Hyderabad) . Andhra Pradesh, India. Phone: (91)4064508536  Email:ima@imaindia.org